MAERSK INVINCIBLE JACK UP RIG

Task carried out

  • Construction method (Rope access) provided to DSME Engineering team
  • Removal of lifting lug, platform, vertical ladder on Jack-up leg
  • Removal of temporary structure on Upper leg
  • Spool, Flex hose, skip selector (SWARF) installation
  • Drape hose & conduit hose installation
  • Mooring, Catcher installation
  • Riser pipe installation
  • Pipe installation in Moonpool
  • CCTV modification / Living quarter cleaning / Commissioning support

ExxonMobil Hebron DES / UPM

HEBRON DES

  • DRILLING EQUIPMENT INSTALLATION
  • PIPING & ELECTIRCAL WORK COMPLETION (Incl. Heat tracing & insulation)
  • COMMISSIONING SUPPORT, MC & PUNCH CLEARANCE WORK

HEBRON UPM – TLQ (TEMPORARY LIVING QUARTER) INSTALLATION

  • ARCHTECTURE, PIPING, ELECTRICAL WORK COMPLETION
  • MC & PUNCH CLEARANCE, COMMISSIONING SUPPORT

Offshore Hook Up & Commissioning

PROJECT

  •  CLOV FPSO IN ANGOLA
  • SNX IN ANGOLA
  • ARKUTUN-DAGI IN SAKHALIN

WORK SCOPE COMPLETED

  • COMMISSIONING
  • STRUCTURE MODIFICATION
  • E&I MODIFICATION
  • PIPING MODIFICATION
  • PAINTING & PRESERVATION
  • PUNCH CLEARANCE

Cobalt Explorer Drillship Derrick assembly & On-board work

SCOPE OF WORK CONTRACTED WITH MHWIRTH

  • DERRICK ASSEMBLY for VANTAGE DRILLING (COBALT EXPLORER DRILLSHIP)
  • ASSEMBLE FROM SKELETON TO ONE-COMPLETION OF DERRICK
  • INSTALLATION OF DRILLING EQUIPMENT
  • INSTALLATION OF ALL PIPING SYSTEM
  • INSTALLATION & COMPLETION OF E&I ITEM
  • PROJECT PERIODS: DEC. 15th, 2014 ~ JUN. 14th, 2015

SCOPE OF WORK CONTRACTED WITH DSME

  • DERRICK ON-BOARD WORK
  • MECHANICAL COMPLETION OF DERRICK

Rig & Drillship Commissioning

  • VERIFICATION OF YARD INSTALLATION (MECHANICAL COMPLETION)
  • YARD SUPERVISION PRE-COMMISSIONING & COMMISSIONING ACTIVITIES
  • INTERNAL LOOP CHECK
  • FUNCTION CHECK
  • SITE ACCEPTANCE TEST
  • SHOOTING COMMISSIONING PUNCH
  • HYDRO TEST
  • HOT OIL FLUSHING
  • CHEMICAL
  • FLUSHING
  • LEAKAGE TEST

BAKER HUGHES

  • MECHANICAL
  • ELECTRICAL
  • PIPING

NOV

  • ARKTUN-DAGI PROJECT MC SUPPORT
  • DRILLING EQUIPMENT MC SUPPORT

EXXON MOBIL

  • OFE EQUIPMENT PRE-COM SUPPORTT

NOBLE

  • NOBLE DISCOVERER PROJECT LEAKAGE TEST, HYDRO TEST & E&I COMMISSIONING
203
204

GE Oil & Gas B.O.P (BlowOutPreventer) Commissioning

  • BOP COMMISSIONING SUPPORT
  • MECHANIC MODIFICATION WORK
  • PIPE MODIFICATION WORK

Baker Hughes Project support

WORK SCOPE COMPLETED

  • MUD & CEMENT UNIT INSTALLATION
  • E&I / PIPING MODIFICATION
  • E&I LOOP TEST
  • EQUIPMENT COMMISSIONING
  • FAT PUNCH CLEARANCE
  • MATERIAL SUPPLY
  • ENGINEERING SUPPORT
baker

Noble Discoverer Drillship

WORK SCOPE COMPLETED

  • CHOKE & KILL LINE MODIFICATION & HYDRO TEST (UNDER 15,000 PSI)
  • NEWLY INSTALLATION OF DECK DRAINAGE SYSTEM INSTALLATION (MORE THAN 600M LENGTH)
  • PIPING PART: MATERIAL PREPARATION, WELDING, INSPECTION, PAINTING & ENGINEERING, ETC.
  • E&I PART: HOT WORK, CABLE PULLING & TERMINATION

National Oilwell Varco project support

PROJECT

  • H3614 ATWOOD ADVANTAGE DRILLSHIP
  • H3617 ATWOOD ACHIEVER DRILLSHIP
  • H3033 ODFJELL SEMI-RIG

WORK SCOPE COMPLETED

  • DRILLING EQUIPMENT MODIFICATION
  • ACTIVE HEAVE COMPENSATOR CRANE’S CYLINDER REPLACEMENT
  • X-MAS CRANE’S ROLLER SWAP WORK & STRUCTURE MODIFICATION
  • RISER CATWALK CART’S ROLLER SHEAVE FABRICATION AND MODIFICATION
  • COMMISSIONING SUPPORT
  • MATERIAL HANDLING & COORDINATION
nov

ExxonMobil Arkutun-Dagi Project

DERRICK ASSEMBLY & ON BOARD WORK

  • FAT PUNCH CLEARANCE
  • CARRY OVER WORK
  • DERRICK & HULL INTERFACE WORK
  • DRILLING EQUIPMENT MC
  • E&I MC & LOOP TEST
  • DIMENSION CONTROL
  • STRUCTURE & PIPING MODIFICATION

 

OWNER CHANGE ORDER WORK

  • Pipe barn and DES Structural modification
  • Abseilers for Gin pole platform bracing
  • Install Crown Platform Fast line Guard
  • ADD Stiffeners and bolt hanger columns
  • Add Infill at Edge of Derrick Cladding
  • Fabricate and Install Cladding Panel
  • Add Skid base Access Ladder at SW Corner
  • Cladding panel modification
  • Replace Derrick-Pipe Barn Cladding Hood
  • Install safety lanyard for Lighting JB
  • Relocate Lighting Fixture
  • Modify Derrick Obstruction Light
  • Install Covers on Exposed Crane Cable Trays
  • Heat tracing Jacket installation
  • Winterization Pipe Installation
  • Modify Ductwork for system 43729

EXXON MOBIL & VENDOR COMMISSIONING SUPPORT

  • ENL Drilling Team
  • NOV, Parker Drilling
  • DRILLING COMMISSIONING punch clearance

Drilling derrick construction

PROJECT

  • H3612 TRANSOCEAN DEEPWATER ASGARD DRILLSHIP
  • H3613 TRANSOCEAN DEEPWATER INVICTUS DRILLSHIP
  • H3031 SONGA SEMI-RIG
  • H3032 SONGA SEMI-RIG

WORK SCOPE COMPLETED

  • DERRICK ASSEMBLY & ON BOARDING (ONTO VESSEL)
  • FAT INSPECTION
  • FAT PUNCH CLEARANCE
  • CARRY OVER WORK
  • DERRICK & HULL INTERFACE WORK
  • DRILLING EQUIPMENT MC
  • E&I MC & LOOP TEST
  • DIMENSION CONTROL
  • STRUCTURE & PIPING MODIFICATION
  • HYDRO TEST

Task carried out

  • Construction method (Rope access) provided to DSME Engineering team
  • Removal of lifting lug, platform, vertical ladder on Jack-up leg
  • Removal of temporary structure on Upper leg
  • Spool, Flex hose, skip selector (SWARF) installation
  • Drape hose & conduit hose installation
  • Mooring, Catcher installation
  • Riser pipe installation
  • Pipe installation in Moonpool
  • CCTV modification / Living quarter cleaning / Commissioning support

HEBRON DES

  • DRILLING EQUIPMENT INSTALLATION
  • PIPING & ELECTIRCAL WORK COMPLETION (Incl. Heat tracing & insulation)
  • COMMISSIONING SUPPORT, MC & PUNCH CLEARANCE WORK

HEBRON UPM – TLQ (TEMPORARY LIVING QUARTER) INSTALLATION

  • ARCHTECTURE, PIPING, ELECTRICAL WORK COMPLETION
  • MC & PUNCH CLEARANCE, COMMISSIONING SUPPORT

SCOPE OF WORK CONTRACTED WITH MHWIRTH

  • DERRICK ASSEMBLY for VANTAGE DRILLING (COBALT EXPLORER DRILLSHIP)
  • ASSEMBLE FROM SKELETON TO ONE-COMPLETION OF DERRICK
  • INSTALLATION OF DRILLING EQUIPMENT
  • INSTALLATION OF ALL PIPING SYSTEM
  • INSTALLATION & COMPLETION OF E&I ITEM
  • PROJECT PERIODS: DEC. 15th, 2014 ~ JUN. 14th, 2015

SCOPE OF WORK CONTRACTED WITH DSME

  • DERRICK ON-BOARD WORK
  • MECHANICAL COMPLETION OF DERRICK

PROJECT

  •  CLOV FPSO IN ANGOLA
  • SNX IN ANGOLA
  • ARKUTUN-DAGI IN SAKHALIN

WORK SCOPE COMPLETED

  • COMMISSIONING
  • STRUCTURE MODIFICATION
  • E&I MODIFICATION
  • PIPING MODIFICATION
  • PAINTING & PRESERVATION
  • PUNCH CLEARANCE
  • VERIFICATION OF YARD INSTALLATION (MECHANICAL COMPLETION)
  • YARD SUPERVISION PRE-COMMISSIONING & COMMISSIONING ACTIVITIES
  • INTERNAL LOOP CHECK
  • FUNCTION CHECK
  • SITE ACCEPTANCE TEST
  • SHOOTING COMMISSIONING PUNCH
  • HYDRO TEST
  • HOT OIL FLUSHING
  • CHEMICAL FLUSHING
  • LEAKAGE TEST

BAKER HUGHES

  • MECHANICAL
  • ELECTRICAL
  • PIPING

NOV

  • ARKTUN-DAGI PROJECT MC SUPPORT
  • DRILLING EQUIPMENT MC SUPPORT

EXXON MOBIL

  • OFE EQUIPMENT PRE-COM SUPPORTT

NOBLE

  • NOBLE DISCOVERER PROJECT LEAKAGE TEST, HYDRO TEST & E&I COMMISSIONING
  • BOP COMMISSIONING SUPPORT
  • MECHANIC MODIFICATION WORK
  • PIPE MODIFICATION WORK

WORK SCOPE COMPLETED

  • MUD & CEMENT UNIT INSTALLATION
  • E&I / PIPING MODIFICATION
  • E&I LOOP TEST
  • EQUIPMENT COMMISSIONING
  • FAT PUNCH CLEARANCE
  • MATERIAL SUPPLY
  • ENGINEERING SUPPORT

WORK SCOPE COMPLETED

  • CHOKE & KILL LINE MODIFICATION & HYDRO TEST (UNDER 15,000 PSI)
  • NEWLY INSTALLATION OF DECK DRAINAGE SYSTEM INSTALLATION (MORE THAN 600M LENGTH)
  • PIPING PART: MATERIAL PREPARATION, WELDING, INSPECTION, PAINTING & ENGINEERING, ETC.
  • E&I PART: HOT WORK, CABLE PULLING & TERMINATION

PROJECT

  • H3614 ATWOOD ADVANTAGE DRILLSHIP
  • H3617 ATWOOD ACHIEVER DRILLSHIP
  • H3033 ODFJELL SEMI-RIG

WORK SCOPE COMPLETED

  • DRILLING EQUIPMENT MODIFICATION
  • ACTIVE HEAVE COMPENSATOR CRANE’S CYLINDER REPLACEMENT
  • X-MAS CRANE’S ROLLER SWAP WORK & STRUCTURE MODIFICATION
  • RISER CATWALK CART’S ROLLER SHEAVE FABRICATION AND MODIFICATION
  • COMMISSIONING SUPPORT
  • MATERIAL HANDLING & COORDINATION

DERRICK ASSEMBLY & ON BOARD WORK

  • FAT PUNCH CLEARANCE
  • CARRY OVER WORK
  • DERRICK & HULL INTERFACE WORK
  • DRILLING EQUIPMENT MC
  • E&I MC & LOOP TEST
  • DIMENSION CONTROL
  • STRUCTURE & PIPING MODIFICATION

OWNER CHANGE ORDER WORK

  • Pipe barn and DES Structural modification
  • Abseilers for Gin pole platform bracing
  • Install Crown Platform Fast line Guard
  • ADD Stiffeners and bolt hanger columns
  • Add Infill at Edge of Derrick Cladding
  • Fabricate and Install Cladding Panel
  • Add Skid base Access Ladder at SW Corner
  • Cladding panel modification
  • Replace Derrick-Pipe Barn Cladding Hood
  • Install safety lanyard for Lighting JB
  • Relocate Lighting Fixture
  • Modify Derrick Obstruction Light
  • Install Covers on Exposed Crane Cable Trays
  • Heat tracing Jacket installation
  • Winterization Pipe Installation
  • Modify Ductwork for system 43729

EXXON MOBIL & VENDOR COMMISSIONING SUPPORT

  • ENL Drilling Team
  • NOV, Parker Drilling
  • DRILLING COMMISSIONING punch clearance

PROJECT

  • H3612 TRANSOCEAN DEEPWATER ASGARD DRILLSHIP
  • H3613 TRANSOCEAN DEEPWATER INVICTUS DRILLSHIP
  • H3031 SONGA SEMI-RIG
  • H3032 SONGA SEMI-RIG

WORK SCOPE COMPLETED

  • DERRICK ASSEMBLY & ON BOARDING (ONTO VESSEL)
  • FAT INSPECTION
  • FAT PUNCH CLEARANCE
  • CARRY OVER WORK
  • DERRICK & HULL INTERFACE WORK
  • DRILLING EQUIPMENT MC
  • E&I MC & LOOP TEST
  • DIMENSION CONTROL
  • STRUCTURE & PIPING MODIFICATION
  • HYDRO TEST